Permit plan · Sand beach or fill at the water's edge

Your permit plan: Sand beach or fill at the water's edge

Based on your answers. Cards are in the order you'll usually need them. Checked Oct 4, 2026.

Your answers (change any of them)
  1. Who owns the water and the lakebed? A state park or Fish and Boat Commission lake · change
  2. Where will the sand or fill go? Only on dry land, not touching the water's edge · change
  3. Is that land in a wetland or a stream's floodway? Not sure · change
State

Individual Chapter 105 permit (Joint Permit Application)

DEP (regional office), or your delegated county conservation district

Fee: Small dam across a stream: DEP fees from $1,750 plus disturbance fees; confirm with DEP.

Chapter 105 work that doesn't qualify for a waiver or a general permit needs an individual water obstruction and encroachment permit through DEP's Joint Permit Application, reviewed by DEP's regional office or a delegated conservation district. DEP recommends a pre-application meeting. In most cases the same application also covers the federal Army Corps authorization. Small dam across a stream: DEP fees from $1,750 plus disturbance fees; confirm with DEP.

What to have ready

  • Ask DEP for a pre-application meeting; DEP recommends it.
  • Expect a site plan, a location map, photos and a project description; larger projects need more (25 Pa. Code § 105.13).

Checked Oct 4, 2026 · Sources: Apply for a Water Obstruction and Encroachment Joint Permit (Chapter 105); Introduction to Ponds and Chapter 105 (FAQ: non-jurisdictional dam across a stream); Pennsylvania State Programmatic General Permit-7 (PASPGP-7), Part I and Part VI (dated April 27, 2026) This may be outdated

Federal

U.S. Army Corps of Engineers (Clean Water Act Section 404)

U.S. Army Corps of Engineers, usually through DEP's joint application

Placing fill or dredged material in waters of the United States, including many wetlands, needs federal authorization under Section 404 of the Clean Water Act. In Pennsylvania the Army Corps and DEP share one joint application: under the Pennsylvania State Programmatic General Permit (PASPGP-7), DEP or a delegated county conservation district can issue both the state and the federal authorization in most cases, and forwards the rest to the Corps. PASPGP-7 runs until June 30, 2031.

Checked Oct 4, 2026 · Source: Pennsylvania State Programmatic General Permit-7 (PASPGP-7), Part I and Part VI (dated April 27, 2026) This may be outdated

State

Erosion and sediment control

Your county conservation district (for DEP)

Any earth disturbance needs erosion and sediment control practices (BMPs). A written erosion and sediment control plan is required once the disturbance reaches 5,000 square feet (or if the work could discharge to a High Quality or Exceptional Value water), and it must be kept on site. Disturbing 1 acre or more generally needs an NPDES permit for construction stormwater. County conservation districts review these plans and may charge a review fee.

Checked Oct 4, 2026 · Source: Frequently Asked Questions: Erosion and Sediment Control (rev. Aug 12, 2026), FAQ #5 This may be outdated

Info

Wetlands nearby? Get them delineated

DEP

If wetlands may exist near a proposed pond or could be affected, DEP says a certified wetland consultant must be hired to identify and delineate the wetlands and watercourses and to prepare the Environmental Assessment. Wetland or stream impacts that cannot be avoided must be replaced (mitigated), which adds cost and time.

Checked Oct 4, 2026 · Source: Introduction to Ponds and Chapter 105 (Impacts to Water Resources; Mitigation) This may be outdated

Also check

Owner

Public lake: the managing agency first

The agency that manages the lake (state park or PFBC)

Talk to the managing agency first; a DEP permit alone isn't enough. A state permit doesn't give you the right to build on public land or water.

A summary, not legal or engineering advice. The regulation, the permit documents and the product label control. Confirm with the agency before you start.

Pros for this work

Optional. We use it only to show pros who serve your area. It isn't saved with your plan.

Get this plan as a PDF, $9

Your cards plus a timeline counted back from your start date, a document checklist for each permit, a call list with links, questions to ask contractors and a tracker. Delivered instantly.

This is not a permit or an application. We don't file anything for you. Agency fees are paid only to the agency.